FSSC 22000 Sanitary Design for Facility Changes

FSSC 22000 sanitary design for facility changes: change approval, layout, cleaning access, verification

Quick answer: Sanitary design for facility changes means reviewing hygiene risks before a new line, layout change or building modification is approved, not after it is installed. A short, structured review inside your change approval process can prevent difficult-to-clean areas and new product-flow conflicts. It also gives you clear evidence for auditors that changes were assessed and verified.

This guide is for FSSC 22000 management system teams, project and engineering leads, sanitation managers and maintenance managers who plan or approve changes at food manufacturing sites.

Why facility changes create hygiene risk

New production lines and facility modifications can unintentionally introduce difficult-to-clean areas or new product-flow conflicts. This usually happens when food safety is considered too late. By the time equipment is bolted down, fixing an inaccessible surface or a badly placed drain is slow and expensive.

An overlooked equipment detail or layout weakness can leave a site with repeat sanitation failures, production interruptions and difficult audit discussions. Even a well-written food safety program is hard to apply when equipment has inaccessible surfaces, damaged seals, unsuitable materials or poorly controlled surroundings. Our FSSC 22000 sanitary design guide explains the wider principles.

What a good change review looks like

A good review is risk-based. It considers the food, the process, product exposure, cleaning frequency and observed performance before deciding on corrective action. In particular, it checks these points:

  • Where food, residues, moisture or allergens could accumulate.
  • Whether routine cleaning and inspection can reach the relevant surfaces.
  • How layout, personnel movement, utilities and maintenance interfaces will change.
  • Records of earlier sanitation failures, equipment repairs and recurring observations on similar equipment.
  • Which expectations are applicable requirements and which are voluntary technical guidance.

Layout decisions deserve particular attention. Our page on layout, product flow and segregation covers the flow principles to protect during a change.

Common problems with facility changes

  • Food safety and sanitation see the drawings only after the purchase order is placed.
  • New equipment is placed without space to clean behind or underneath it.
  • Drain capacity is not checked for added wet cleaning or process water.
  • Temporary construction work creates dust, debris or traffic through exposed-product areas.
  • The change is closed without checking cleaning results before routine production.
Six steps for sanitary design for facility changes: screen early, review drawings and flows, check cleaning access, document risks, approve controls, verify before production

Six steps to build sanitary design into change approval

1. Screen the change early

Add a simple hygienic design question to your change request form. If the change affects equipment, layout, utilities or drainage, it should trigger a review. Our article on FSSC 22000 change control explains how to structure that wider process.

2. Review drawings and flows

Consider layout drawings, the intended cleaning methods and movement of people, materials and waste. Look for new crossings between raw and finished product or between allergen and non-allergen areas.

3. Check cleaning access and maintenance needs

Confirm equipment access, drain capacity and maintenance needs. Ask the sanitation and maintenance teams how they will clean and service the new installation.

4. Document risks and owners

Record the observed or expected condition, the affected process, the potential hazard and supporting evidence. Then assess severity and likelihood in the real facility context, and assign owners and deadlines.

5. Approve suitable controls

Approve engineering or procedural changes with input from food safety, sanitation, operations and maintenance. Where construction takes place near production, agree temporary controls as well. The page on risk zone hygiene controls helps define what each area needs.

6. Verify before routine production

Check the completed work and keep objective evidence that problems were addressed. Post-installation verification, such as an inspection and a first cleaning check, should happen before routine production begins. Our page on start-up and changeover procedures shows how to connect this to start-up.

Records and evidence to keep

  • The change request with the hygienic design screening answer.
  • Reviewed drawings, comments and decisions.
  • A risk assessment with owners and target dates.
  • Temporary control records during construction or installation.
  • Post-installation inspection and cleaning verification results.
  • Sign-off for release to routine production.

Example scenario

A ready meals plant plans to add a second packing line in an existing room. The change form flags layout and drainage, so the food safety team joins the design review. During the review, sanitation points out that the new line would sit too close to a wall for cleaning. In addition, maintenance confirms the nearest drain cannot handle the extra wash-down water.

Consequently, the project team moves the line and adds a drain before installation. After installation, the team inspects the area, completes a first cleaning check and records the results. Only then is the line released for routine production.

Sanitary design for facility changes checklist

  • The change form includes a hygienic design screening question.
  • Food safety, sanitation and maintenance review drawings before approval.
  • Cleaning access, drain capacity and utilities are checked for the new layout.
  • Product, people and waste flows are reviewed for new crossings.
  • Temporary construction controls are agreed where production continues.
  • Post-installation verification is completed before routine production.

Frequently asked questions

Does every small change need a sanitary design review?

Not every change needs a full review. However, a short screening question helps decide which changes affect equipment, layout, utilities or drainage and need more attention.

When should outside support be considered?

It can help when the same condition keeps returning despite corrective actions, or when an expansion creates uncertainty about hygienic design expectations. It also helps when a team needs to coordinate evidence before a customer or certification audit.

Who approves the final change?

Facility management approves and implements changes. Food safety, sanitation, operations and maintenance provide the input needed for a sound decision.

How Consultare Inc. Group can help

Consultare Inc. Group supports management-system documentation, change-control workflows, prerequisite program gap reviews and commissioning-readiness planning. Typical activities include a kickoff discussion, review of procedures and evidence, agreed observations or interviews, a prioritized improvement register and action-tracking support. Exact deliverables depend on the approved scope. We do not promise certification, regulatory approval or an audit outcome.

Need help managing your FSSC 22000 responsibilities?

Discuss your products, process, records, risks and next steps with our team. Contact us or book a free consultation.

Prefer to organize your compliance activities yourself? Create a free SystemsBuilder account to structure change requests, risk reviews and corrective actions.

Technical sources: FSSC 22000 and EHEDG (voluntary hygienic design guidance). This article is educational; requirements depend on your products, certification scope and applicable regulations. Food Safety Systems is an independent consultancy and is not affiliated with the FSSC 22000 Foundation or FDA.

Scroll to Top